TEST YOUR SKILLS WITH AACE INTERNATIONAL AACE-PSP WEB-BASED PRACTICE EXAM SOFTWARE

Test Your Skills with AACE International AACE-PSP Web-Based Practice Exam Software

Test Your Skills with AACE International AACE-PSP Web-Based Practice Exam Software

Blog Article

Tags: New AACE-PSP Exam Sample, Exam AACE-PSP Materials, Reliable AACE-PSP Test Simulator, Valid Dumps AACE-PSP Sheet, Reliable AACE-PSP Test Review

What's more, part of that Dumps4PDF AACE-PSP dumps now are free: https://drive.google.com/open?id=1Q2qykmMVdtKoKXI-btNUIuyVnO_wN9qg

In order to cater to different needs of customers, three versions for AACE-PSP training materials are available, you can choose the most suitable one in accordance with your own needs. AACE-PSP PDF version is printable, and if you prefer a hard one, you can choose this version. AACE-PSP Soft test engine supports MS operating system, and it can install in more than 200 computers. AACE-PSP Online Test engine is convenient and easy to learn, you can have offline practice if you want. AACE-PSP Online soft test engine supports all web browsers and it has testing history and performance review, and you can have a general review of what you have learnt before next learning.

To obtain the AACE-PSP certification, candidates must meet specific educational and experience requirements, as well as pass a rigorous examination. AACE-PSP exam covers a broad range of topics, including cost estimating, planning and scheduling fundamentals, progress and performance measurement, risk management, and leadership in project management. Planning & Scheduling Professional (PSP) Exam certification validates a professional’s abilities to develop effective project schedules, analyze project performance, and communicate project status effectively with stakeholders. Additionally, certified professionals are required to maintain their certification through ongoing education and training, ensuring that they remain up-to-date with the latest advancements and best practices in their field.

AACE International AACE-PSP (Planning & Scheduling Professional) Exam is a certification program that is designed to validate the skills and knowledge of individuals working in the planning and scheduling field. Planning & Scheduling Professional (PSP) Exam certification is recognized globally and is highly valued by employers in the industry. The AACE-PSP Exam covers a wide range of topics, including project planning and control, scheduling, cost management, risk management, and project communication.

>> New AACE-PSP Exam Sample <<

100% Pass 2025 Latest AACE International AACE-PSP: New Planning & Scheduling Professional (PSP) Exam Exam Sample

Our materials can make you master the best AACE-PSP questions torrent in the shortest time and save your much time and energy to complete other thing. What most important is that our AACE-PSP study materials can be download, installed and used safe. We can guarantee to you that there no virus in our product. Not only that, we also provide the best service and the best AACE-PSP Exam Torrent to you and we can guarantee that the quality of our AACE-PSP learning dump is good. So please take it easy after the purchase and we won’t let your money be wasted.

How to book the Planning & Scheduling Professional (PSP) Exam

Follow the steps mentioned below to book the Planning & Scheduling Professional (PSP) Exam:

  • Step 1: Visit the AACE's website by clicking here
  • Step 2: Create a new account or log in to an existing account
  • Step 3: Select your professional exam
  • Step 4: Complete the required course and take PSP practice test
  • Step 5: Fill the application and submit all required documents
  • Step 6: Schedule your exam by following the instructions on the website

AACE International Planning & Scheduling Professional (PSP) Exam Sample Questions (Q127-Q132):

NEW QUESTION # 127
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

  • A. 09-08-01.
  • B. 09-28-01.
  • C. 09-18-01.
  • D. 09-15-01.

Answer: A


NEW QUESTION # 128
Using the normal schedule, what is the owner's total cost of the project?

  • A. S12.990.000
  • B. S12.953.600
  • C. S13.990.600
  • D. S13.102.900

Answer: B


NEW QUESTION # 129
Scenario:
The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

PSP Activities Table
Scope Known about Rock-Filled Dam Project:
The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.
Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the
"normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.
The following table lists work activities as planned by the contractor.

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?

  • A. $524,000.
  • B. $420,000.
  • C. $552,000.
  • D. $307,000.

Answer: C


NEW QUESTION # 130
Under which circumstance should one perform resource-leveling calculations?

  • A. When the contract contains a provision for float-banking.
  • B. When the schedule is resource-loaded.
  • C. When you believe that known resource limitations may override schedule logic.
  • D. Never, unless required by the contract.

Answer: C


NEW QUESTION # 131
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?

  • A. 13.
  • B. Cannot be determined.
  • C. 12.
  • D. 14.

Answer: C


NEW QUESTION # 132
......